Per AGENTS.md -> Current status and next work, the spec is ready to plan for Phase 0/1 (design + assisted MVP) and the Phase 2 framework (ledger engine, state machines, data model, API, reconciliation). But §16 of docs/architecture/README.md still lists a set of decisions that are Provisional or Open. Each dependent on the executed DCA term sheet, German counsel, tax advice, or accounting confirmation:

ID Topic Status
D-01 True sale with fixed deferred price (Option A2) Provisional
D-03 Assignment notice sent by DCA Open
D-04 Gross funding + VAT model Provisional
D-05 DCA's KWG factoring licence confirmed Open
D-06 DCA-owned trust/collection account Provisional
D-07 Collection waterfall / fee order Provisional
D-08 Repurchase mechanics (pro-rata denominator) Provisional
D-11 ZAG position — PSP holds no client funds Provisional, go-live blocker
D-13 Minimum fee (provisional min_fee = 0) Provisional
W-01 Write-offs DCA-owned, not PSP-booked Provisional
S-01 Settlement header + lines (DCA statement format) Provisional

Ask

  1. Track each item above with owner and target date; evidence per §16.1 (executed term sheet, counsel opinions, tax advice, accounting confirmation).
  2. Give D-11 (ZAG) its own milestone. It gates go-live.
  3. Keep the upcoming framework plan term-sheet-agnostic: min_fee, DCA share %, D-08 pro-rata repurchase denominator, D-07 fee order, and the DCA statement/remittance format must live behind configuration/contracts, not hard-coded placeholders.
  4. Do not scope full production automation of money movement until the Provisional decisions move to Decided.
Per `AGENTS.md` -> *Current status and next work*, the spec is ready to plan for Phase 0/1 (design + assisted MVP) and the Phase 2 framework (ledger engine, state machines, data model, API, reconciliation). But §16 of `docs/architecture/README.md` still lists a set of decisions that are **Provisional** or **Open**. Each dependent on the executed DCA term sheet, German counsel, tax advice, or accounting confirmation: | ID | Topic | Status | |---|---|---| | D-01 | True sale with fixed deferred price (Option A2) | Provisional | | D-03 | Assignment notice sent by DCA | Open | | D-04 | Gross funding + VAT model | Provisional | | D-05 | DCA's KWG factoring licence confirmed | Open | | D-06 | DCA-owned trust/collection account | Provisional | | D-07 | Collection waterfall / fee order | Provisional | | D-08 | Repurchase mechanics (pro-rata denominator) | Provisional | | D-11 | ZAG position — PSP holds no client funds | Provisional, **go-live blocker** | | D-13 | Minimum fee (provisional `min_fee = 0`) | Provisional | | W-01 | Write-offs DCA-owned, not PSP-booked | Provisional | | S-01 | Settlement header + lines (DCA statement format) | Provisional | **Ask** 1. Track each item above with owner and target date; evidence per §16.1 (executed term sheet, counsel opinions, tax advice, accounting confirmation). 2. Give D-11 (ZAG) its own milestone. It gates go-live. 3. Keep the upcoming framework plan term-sheet-agnostic: `min_fee`, DCA share %, D-08 pro-rata repurchase denominator, D-07 fee order, and the DCA statement/remittance format must live behind configuration/contracts, not hard-coded placeholders. 4. Do **not** scope full production automation of money movement until the Provisional decisions move to **Decided**.
Sign in to join this conversation.
No labels
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
sid/psp#1
No description provided.